West Virginia Approves $1.18 Monthly Surcharge for Maidsville Energy Center
The West Virginia Public Service Commission has approved a $1.18 monthly residential surcharge to fund the $2.48 billion Maidsville Energy Center, a 1.2-GW gas plant with 70 MW of solar. The project aims to meet surging data center demand, with the surcharge lasting until the plant becomes operational in late 2031.

The West Virginia Public Service Commission approved a $1.18 monthly residential surcharge to fund the Maidsville Energy Center project on November 17, 2026. The construction surcharge will increase residential bills by 0.9% initially.
The commission stated the surcharge mechanism had been used before, including for the canceled Mid Atlantic Power Pathway by Pepco Holdings, which recovered more than $80 million from ratepayers. It said the mechanism would prevent any credit downgrading due to lack of funds from operations flowing in. In the unlikely event construction ceases or experiences extraordinary delays, the commission will initiate a proceeding to determine accounting and ratemaking treatment and timing of recovery.
Project details and capacity needs
The project is a 1.2-GW combined-cycle natural gas-fired power plant with 70 MW of solar, located in West Virginia. It was prompted by an unnamed data center customer requiring 100 MW initial capacity in 2028, increasing to 1,012 MW by 2033.
Mon Power projected a 2,997 MW summer peak in 2026 and a 60 MW capacity shortfall in 2028. That capacity shortfall is projected to grow to 2,194 MW in 2034 with new large loads, including data centers.
Cost and funding structure
The total cost of the Maidsville Energy Center is $2.48 billion. FirstEnergy plans to fund about 35% of the project with equity or equity-like securities, lifting its expected equity needs for 2026-2030 to $2.8 billion from $2 billion. The company is seeking a low-interest Department of Energy loan that could save customers about $217 million for each $1 billion guaranteed over 30 years.
FirstEnergy raised its 2026-2030 capital plan to $38 billion from $36 billion after the approval. The higher plan lifts its expected rate base growth to 11.1% a year from 10.4%.
Regulatory and financial safeguards
The surcharge will be calculated every six months based on actual construction-work-in-progress balances. It will run until the assets are included in base rates after the gas plant comes online, expected on December 31, 2031. The solar projects are due between 2027 and 2030.
The order allows Mon Power a 9.8% return on equity on a 50/50 debt and equity structure. FirstEnergy expects to sign gas supply and engineering, procurement and construction contracts in the fourth quarter and start site preparation in the first quarter of 2027.
Groups like the Sierra Club argued that the utility’s $4 billion rate base would increase by 67% as a result of the project. Anna Sommer, an expert witness in the case, highlighted project risks, stating, "The underdevelopment of the Companies’ CC proposal introduces significant risk of cost increases and schedule delays."
FirstEnergy raised its long-term core EPS growth outlook to 7% to 9% a year through 2030, targeting the upper half of the range. The company issued an initial request for proposals for another 3 GW of combined-cycle gas plants and is exploring bridge power and temporary behind-the-meter options, with an update expected in early 2027.
It expects to raise transmission investment by at least 25% from the current $19 billion plan when rolling the plan forward to 2027-2031 in February. The report mentions large load connections for data centers and AI among its transmission projects.
The surcharge will be recalculated every six months based on construction progress until the gas plant comes online in late 2031.