Data Center Slowdown Risks Billions in Utility Investment

A wave of local restrictions and political shifts is slowing data center construction, jeopardizing billions in utility infrastructure spending planned for AI-driven demand. An estimated 191 gigawatts of planned capacity faces new risk, concentrated in Texas, Ohio, and Georgia.

A wave of local restrictions and political shifts is slowing data center construction, jeopardizing billions in utility...

A sharp slowdown in data center construction threatens utility capital plans and grid reliability as uncertainty around artificial intelligence demand grows. Utilities could be left holding the bill for billions in infrastructure spending committed in anticipation of data centers that are now delayed, downsized, or canceled. This slowdown could reduce future utility infrastructure spending and cut into orders for electrical equipment.

Nearly all 46 municipal ballot measures tracked on data center development resulted in restrictions, moratoriums, or bans. An estimated 191 gigawatts of planned data center capacity now faces new risk, with exposure concentrated in Texas, Ohio, and Georgia.

Midterm results add pressure on early-stage investments

Democratic gains in the midterm elections are adding pressure on earlier-stage data center investments across key markets. The results pose only modest risks to current AI investment, however, with potential moratoria likely affecting only projects not yet permitted.

Texas faces concentrated risk with half of planned capacity exposed

Texas accounts for nearly half of the pre-construction data center capacity in development in the United States. Governor Greg Abbott announced a pause on new data center interconnections pending an audit of the queue, quietly implementing a permitting pause in Austin. He lost his bid for reelection to Democrat Gina Hinojosa, who has pledged to maintain pressure on the industry after taking office next year.

Regulatory and political headwinds slow development

Opposition to data center construction has crossed traditional party lines. Newly elected politicians in Ohio, Georgia, and Texas may influence development, but federal officials have limited control over state-level outcomes. The regulatory environment in Texas may remain stable unless key officials step down or are ousted. Louisiana Governor Jeff Landry and Oklahoma are actively courting data center businesses as potential alternatives.

Utilities face new tariff requirements and capacity commitments

Utilities are implementing new rules to manage risk. AEP Ohio’s large-load tariff, approved in July 2025, requires new data centers above 25 megawatts to pay for at least 85% of requested capacity for up to 12 years, with exit fees and financial guarantees. This caused the utility’s data-center pipeline to fall by more than half.

Stage of RequestCapacity (Megawatts)
Initial developer requests30,000+
Proceeded to studies after new requirements13,023
Contracted after February 20265,642
Contracted before July 2025 tariff12,219

Richard Caperton, vice president of policy at SPAN, anticipates greater emphasis on data center projects that can be served without major new grid investments. Governor Spanberger signed legislation requiring Dominion Energy and Appalachian Power to report how effectively they use existing grid infrastructure. Louisa Eberle, principal at the Regulatory Assistance Project, warned that "existing tariffs and regulatory frameworks likely won’t fully protect customers because they were designed for a different century."

The financial implications are significant. If 20% of projected data center demand in the Electric Reliability Council of Texas region fails to materialize, solar and wind generators could see their average wholesale revenue fall 38% and 37%, respectively. Implied heat rates could decline 39%. In the PJM grid region, delaying half of the planned data center buildout by two years could reduce four-hour battery storage arbitrage spreads by 16% and lower solar and wind capture prices by about 12% through 2030.

Despite concerns, some industry voices remain optimistic. The Edison Electric Institute's annual conference featured utility CEOs stating data center slowdown concerns are overblown. Andy Roehr of Baker Tilly’s energy and infrastructure practice sees developers as more likely to redirect capital than abandon projects due to permitting hurdles. Stephen Rose, CEO of infrastructure software provider Render Networks, expects to see a pause and necessary shakeout in development.

Equipment maker Eaton reported that orders from data center customers across its electrical businesses more than doubled over the preceding 12 months in the third quarter. The company ended the quarter with $26.2 billion in firm orders awaiting delivery. American Electric Power expects 84 gigawatts of incremental contracted load by 2031 from data center development.