New Jersey utilities race to launch virtual power plant program
New Jersey's four regulated utilities must implement interim virtual power plant programs by October 2027, aiming to cut peak demand by 3% using customer-owned devices like batteries and smart thermostats.

New Jersey’s four regulated utilities have less than 11 months to implement the state’s new virtual power plant program. The New Jersey Board of Public Utilities set an October 1, 2027, deadline for operating interim versions of the PowerUp NJ program following its approval on November 12, 2026.
Participating utilities include Public Service Electric and Gas, Atlantic City Electric, Jersey Central Power & Light, and Rockland Electric. They must submit their specific PowerUp NJ programs for regulatory review by February 12, 2027. The utilities began laying groundwork for the initiative early this year after Governor Mikie Sherrill’s Inauguration Day orders to accelerate clean power deployment in the PJM Interconnection region.
Eligible technologies include smart devices and battery storage
PowerUp NJ is technology neutral, accepting a wide range of customer-owned devices. Eligible equipment includes smart thermostats, stationary home batteries, internet-connected electric water heaters, vehicle chargers, and electric vehicles. The program also extends eligibility to net-metered solar-plus-storage systems. Solar-only systems that receive net-metering credits are not eligible for this interim virtual power plant program.
Program targets 3% peak demand reduction through distributed resources
The initiative aims to reduce grid stress and mitigate power price spikes by shifting load from demand peaks. It targets both local distribution-level events and broader PJM capacity and transmission peaks. A 3% cut to peak demand across the four utilities, equivalent to 547.1 megawatts, could avoid $60 million in annual system capacity costs. This reduction would also lower emissions from fossil-fueled peaker plants. The program aims to reduce reliance on expensive peak-generation resources during high-demand periods.
Incentives support 150MW new and 100MW existing battery storage
Specific incentives target battery storage expansion to support the state's broader energy storage goals. New Jersey aims to develop 2,000 megawatts of energy storage capacity by 2030. The PowerUp NJ program separately targets 150 megawatts of new distributed battery storage and 100 megawatts from existing systems. Battery storage programs must become operational within 60 days of utility program approval.
| Storage Type | Target Capacity | Maximum Annual Incentive |
|---|---|---|
| New Battery Storage | 150 MW | $200 per kilowatt |
| Existing Battery Storage | 100 MW | $100 per kilowatt |
Incentives for battery storage can continue for 10 years, with actual earnings dependent on performance during utility-called events. A 10-kilowatt new battery system could earn up to $2,000 annually, totaling $20,000 over a decade.
Customer opt-in allows device selection to avoid discomfort
Participation is entirely voluntary. Customers must opt in to PowerUp NJ. Once enrolled, they can choose which of their eligible devices to include and can select which utility events to participate in to avoid discomfort. Customer enrollment and payments will follow implementation steps after individual utility programs are developed.
The BPU’s order this month cements program features from a July straw proposal, including a market-based framework for compensating distributed energy resources for grid services. BPU President Ben Hertz-Shargel stated the agency will apply lessons from the two-year interim version to develop a long-term framework. "We will develop this program carefully, learn from real-world results, and expand it over time, growing the earnings opportunities for residential and business customers," Hertz-Shargel said.
Utilities must submit PowerUp NJ programs for regulatory review by February 12, 2027.